Concept illustration of a coordination review; it does not depict a customer project or prescribe joint dimensions.
A facade elevation shows a neat panel grid. The fabrication drawing shows the same grid, yet one joint meets a window return in a different place. If the panels are cut from the uncoordinated drawing, a correct finish and a correct order will not resolve that mismatch on site.
Before releasing ACP panels for fabrication, agree which drawing controls the joint layout. Check the grid against openings, corners, movement provisions and the intended fixing system, then record who has accepted each remaining deviation. This is a drawing-release decision, separate from approving a colour sample.
Use one controlled elevation
Put the latest architectural elevation, measured site information where required, and the fabricator’s panel layout side by side. Mark the revision and date on each. A dimension copied from an earlier drawing can look plausible until a window schedule or substrate survey changes. Where dimensions are still provisional, label them as such and hold the affected panels rather than treating the whole elevation as approved.
The technical submittal checklist helps keep the product specification and drawing revisions together. The joint layout still needs its own review by the project team responsible for the facade design and installation.
Review the locations that change a panel
Walk the drawing from one datum through the full elevation. At each opening, return, corner and change of plane, ask where the visible joint lands and which panel carries the edge. Check that the panel identity on the drawing matches the fabrication schedule. A repeated module may hide one exceptional panel at an end bay.
Record the intended joint width and allowance only from the approved project design and the applicable system details. Do not infer them from a concept sketch or a photograph. The installer or facade engineer should resolve support, movement and water-management details under the project’s design process.

Close exceptions before cutting
A useful release record names the location, the conflicting references, the proposed resolution and the approving party. If a joint moves, update the affected panel dimensions and identifiers in the fabrication schedule. If a site measurement is pending, keep those panels on hold. Do not allow a verbal instruction to become the only record of a changed grid.
Once the layout is released, the routing and folding pre-fabrication checklist covers the next decision: whether the approved geometry has been translated into the correct shop process. For a new ACP selection, start with the ACP product overview and confirm the project-specific system requirements.
Questions project teams ask
Is colour-sample approval enough to release the panel grid?
No. A sample controls the agreed appearance reference. The panel layout, dimensions and joint locations require drawing coordination and a separate release.
What if the site measurement differs from the elevation?
Identify the affected area and panel IDs, ask the responsible designer and installer to resolve the discrepancy, and revise the controlled drawing before those panels are fabricated.
Should every panel wait if one opening is unresolved?
That depends on whether the unresolved dimension affects other panels or the common datum. Record the boundary of the hold and release only work whose geometry is independently agreed.
What should accompany the fabrication release?
Keep the approved drawing revision, panel schedule, exception log and named approvals together. Add project-specific system details and measurements required by the responsible team.
If your facade drawing and panel schedule are ready for supplier review, send the current revisions and identify the unresolved joints. Jinxiang can discuss the ACP product and fabrication information needed for your project; final design and installation approval remain with the project team.